Ground floor Steel Frame erected 17th October 2014

Today, Northern Structures Limited started work erecting the ground floor steelwork, this will be completed tomorrow. Following on from this will be the poured concrete 1st floor which will carry the timber frame. The timber frame is due on site 3rd November.

 