Roof and Windows Completed 03/02/2015

At last we have had good enough  weather to get the roof complete (apart from 3 small flashings) and today we will be installing the last of the large sliding balcony Doors, completing the windows installation. If weather permits our next big job is to get the cladding completed and the scaffolding down, hopefully by the next diary entry!

Also happening this month, is first fix joinery, first fix electrics and plumbing ready for plasterboarding in March, and we are still aiming for  the first apartment to be completed by the end of April.

 

 

 

 

 

 

 

 

 

 

 

Coble Quay is now advertised on Right Move and we have had several enquiries from the Rightmove Site.

Brochures are available from either Sam Allan Estates or the site office at Coble Quay

< back

Download our Latest Brochure

brouchure

Download Now >

Virtual Tour

Take a tour around one of our new two bedroom Apartments in Block 4 at Coble Quay

 

Development Diary

2nd August 2018 It has been a busy few months

Read More >

1st March 2018 A view you often don't see in Amble

Read More >

Contact us

Coble Developments Ltd
The Boatyard
Coquet Street, Amble
Northumberland
tel: 01665 714 607
email: info@cobledevelopments.co.uk